BCA Engineering Group together with the General Contractor has completed the implementation of the Data Center facility for an international client. As expected, comprehensive tests were carried out by an international team. Our team, together with the General Contractor's team, was very positively evaluated by the foreign teams, which confirmed our extensive knowledge and expertise in implementing projects in an international environment.
Our scope included the management of the commissioning process in cooperation with the Investor's representatives as well as the provision of all necessary test equipment for the implementation of the task. The entire work lasted over 8 months, of which 4 months were intensive tests under load.
We look forward to further interesting projects implemented in Poland with foreign Investors.