Completion of the rinsing service for ice water installations for the Data Centre Warsaw facility

We have successfully completed another order entrusted to us at the Data Centre WA03 in Warsaw.

This time we carried out a complicated process of chemical cleaning of pipelines for a 55m3 refrigeration system.

Comprehensive flushing of the installation was performed using dedicated external circulation pumps and dedicated chemicals.

All work was carried out in accordance with the guidelines of the British BSRIA Guide, under the supervision of foreign experts. The works were completed in accordance with the guidelines of the Investor and the project team.

If you have questions about flushing water installations, please contact us at link.

News
Ask a question
Expert Advice

If you have a technical question
about Data Centers, we will be happy to help.

  • Free of charge
  • Feedback within 24h
  • Experts, Technicians